Glen Manor Tentative Schedule
Florida Painters will begin painting the exteriors of Glen Manor October 14th, 2024.
We are aiming to complete about two buildings every week. Beginning on the South side of the community, we will start at building 8 and work counter clockwise to building 15. Crossing the street to the North end, we will move counter clockwise from building 5 and finish on building 4.
We will begin painting lanais on October 28th and follow the same order. Please Note: This is a tentative schedule and is likely to change due to weather and other unforeseen issues.