Glen Manor Tentative Schedule
Florida Painters will begin painting the exteriors of Glen Manor September 30th, 2024.
We are aiming to complete two buildings every week. Beginning on the South side of the community, we will start at building 8 and work counter clockwise to building 15. Crossing the street to the North end, we will move counter clockwise from building 5 and finish on building 4.
* Mondays = Pressure washing
* Tuesdays = Lanai walls and ceilings
* Wednesdays = Lanai floors
* Thursdays = Unit doors
* Friday = Steps